NJ: Inadequate power, easement further delays Mahwah cell tower installation [telecom]
Marsha A. Stoltz NorthJersey.com
MAHWAH - Inadequate power and uncertainty about where new power lines would be installed will further delay the installation of a temporary cell tower at Fire Company 3 by eight weeks, the township's consultant said.
AT&T had agreed in its Dec. 22 lease agreement to have a temporary tower up "within two months." However, since the Jan. 21 Township Council meeting, officials have been signaling the probability of further delays.