|
Posted by on September 25, 2006, 7:32 pm
Just say no!!!!! If you think a contractor is milking you and
charging extra just say no. Remind them of the contract you signed
and his estimate. If he balks remind him that he is not going to be
paid until deck is X% finshed and then final payment is made upon
finishing,. You do have a signed contract right? You did check
references? If you keep letting it go the deck will cost a lot more
than the estimate.
orangele2003nut@yahoo.com wrote:
> I found a local contractor to build a deck for me out of a imported
> exotic hardwood (ipe). The project involved removing an existing deck
> and rebuilding it. He did seem to be very knowledgeable and
> enthusiastic. He quoted me a price (labor only) approximately 70%
> more than two other contractors because he did his research and knew
> that this wood is difficult to work with. The suppliers of the wood
> estimate labor costs approximately 50% higher than using a traditional
> deck wood, so I did not think his estimate was totally unreasonable.
> The other two contractors have never heard of ipe wood, and I believe
> simply ignorant of the difficulty in working with this EXTREMELY hard
> dense wood (all screws and holes must be predrilled, and cannot hammer
> through this wood). I accepted his bid without haggling, and I told
> him that I expected that he was a master craftsman, and I expected that
> he is an expert, and that is why I would pay him top dollar. He
> quoted me a time estimate of 2 1/2 weeks to complete the deck.
>
> Since beginning he has taken every opportunity to charge me extra labor
> costs. Firstly, on demolition of the existing deck, he said that the
> existing deck posts were deeper than anticipated, and so he charged me
> rental for a larger jack hammer than he had, and charged me $650 extra
> ($65 an hour for extra 10 hours). I told him that I was not pleased,
> but agreed for him to proceed. I do not know exactly how much EXTRA
> time (beyond what he expected and should have been covered by the
> original bid) but I seriously doubt it was 10 hours.
>
> Then when I discovered that the wood supplier would not unload the
> delivery truck, he said he wanted to unload it, and that he needed a
> fork-lift (approximately 6000 lbs total weight of wood). The
> supplier told me that there were about 5 batches of wood. I told him
> to go ahead, and that I could not imagine that it would take more than
> an hour to unload the truck using a fork-lift. Well after this
> occured, he charged me 2 1/2 hrs labor (this time he charged $75 an
> hour) time. When I said that I could not understand how it could have
> taken 2 1/2 hours to unload with a fork-lift, he said he examined each
> piece of wood, and that is why it took that length of time. When I
> complained, he asked if I wanted him to just accept lousy wood, I told
> him I felt that examining the building materials should included in his
> original labor bid. But I went ahead and paid him.
>
> He has worked on the project a total of 4 days, and the posts, and
> joists are all up and now he says he will be finished within a week.
>
> I find it very f**ked-up, that he takes every opportunity to charge me
> additional labor costs when he says a particular step is taking longer
> than anticipated, but when and if he finishes the project in less than
> half the time he said it would, why should not I request a 50% return
> of the labor costs he bid. Obviously, the overall labor time is way
> less than he proposed to me, why am paying for extra labor costs. Do
> all contractors pay this game, and how can I prevent this in the future?
|